Construction status
Thanks to all generous sponsors we have managed to gather the necessary funds to start the construction of the main part of the cabin. The construction work of the main started in October 2009 and if the weather is good it should end when the snow melts. What needs to be done still:
- shower
- elevation
- some smaller details
External elevation - 15 April 2010
Inside - 30 January 2010
Door and windows - 15 December 2009
Insulation - 10 December 2009
Covering the roof - 27 November 2009
Roof construction - 24 November 2009
Finishing the central part - 17 October 2009
Foundation is ready - 6 August 2008
Building the cesspit - 3 August 2008
Connecting water and electricity - 30 July 2008
Laying the foundations - 15 July 2008
Preparing the site - 10 July 2008
Preparation work - 5 July 2008